If an activity on the critical path takes longer than anticipated, then ( )
A、Activitiesnotonthecriticalpathhaveadditionalslack
B、Activitiesnotonthecriticalpathhavelessslack
C、Additionalcriticalpathactivitieswillappear
D、Noneoftherest